How to Size a Generator (kVA) Correctly — With Worked Examples
Getting genset sizing wrong leads to two problems: too small and it trips, too large and it burns fuel for nothing. Here is the method our engineering team uses.
Sizing a genset is not simply adding up nameplate ratings. What usually decides the size is not the running load but the starting surge of the largest motor. Many gensets trip on day one because this step was skipped.
1. Running load
Add the rated kW of everything that genuinely runs at the same time, then divide by the average power factor. For mixed building loads, 0.8 is a safe assumption. That gives running kVA.
2. Largest motor starting surge
Induction motors draw several times rated current at start: roughly 6× direct on line, 3× star-delta, 2.5× soft starter and only about 1.2× on a VSD. Take the largest motor, work out its starting kVA and add it to the kVA already running.
3. Diversity factor
In a real building not everything runs at once. A diversity factor of 0.7–0.9 is reasonable for commercial buildings, but use 1.0 for data centres and hospitals, where every critical load must be ready simultaneously.
4. Site derating and growth margin
Output falls in hot, high locations: about 1% per 100 m above 300 m elevation and 2% per 5 °C above 40 °C. Add a 10–25% growth margin if the plant will expand, then round up to the nearest standard rating.