The need
A data centre in Cikarang needed large-capacity backup power that takes over the moment the grid fails, without disturbing running servers.
What we did
We supplied a 2,700 kVA Yuchai-powered generator, ran the power cabling to the distribution panel, then tested automatic start and load transfer with the facility team.
The result
The unit was handed over after a load test with a signed report, and our team continues to support routine maintenance of the generator room.